Project Duration

14
Days

Project Background

The project was located in the childcare center and the tiling service was provided for the bathroom area.

Problems we met

There was nowhere to dispose the wastewater. Besides, the glass-made mosaic to be installed was too thin and small to be cut.

Solution & Result

We applied sedimentation in wastewater treatment. And the solids and water was disposed separately to avoid pollution. In terms of installing the specific mosaic, the aluminum trims were added at the external corner to make the surface flat and smooth as well as to present an aesthetic appearance.